New parking structure designed for drainage basin to accommodate drainage of 10 acres

The location of the new structure on the sole remaining parcel on the east edge of campus is located within a major drainage basin for the surrounding area. This drainage basin will accommodate drainage of 10 acres from the east neighborhood and four acres from the adjacent church drain to the property and will require storage of approximately 150,000 cf of water, as calculated by 50- and 100-year event release rates.